Original Budget
$132m
Current Cost
$180m
Cost Overrun
37.0%
49m
Schedule
+12 months
Sector Justice & Emergency
Responsible Entity Department of Justice and Community Safety
Status In Progress
Original Completion 30 Jun 2025
Current Completion 30 Jun 2026
Scope Changes 0 recorded
Cost RAG Off Track
Time RAG Off Track
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.