Original Budget
$8m
Current Cost
$11m
Cost Overrun
31.3%
3m
Schedule
+27 months
Sector Information Technology
Responsible Entity Wannon Region Water Corporation
Status In Progress
Original Completion 22 Mar 2024
Current Completion 30 Jun 2026
Scope Changes 0 recorded
Cost RAG At Risk
Time RAG Off Track
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.