Original Budget
$22m
Current Cost
$19m
Cost Overrun
-11.1%
-2m
Schedule
+1 months
Sector Information Technology
Responsible Entity Department of Justice and Community Safety
Status In Progress
Original Completion 30 Jun 2025
Current Completion 30 Jul 2025
Scope Changes 0 recorded
Cost RAG At Risk
Time RAG At Risk
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.

View full project detail →