Original Budget
$10m
Current Cost
$14m
Cost Overrun
48.5%
5m
Schedule
+39 months
| Sector | Justice & Emergency |
| Responsible Entity | Department of Justice and Community Safety |
| Status | In Progress |
| Original Completion | 21 Apr 2022 |
| Current Completion | 23 Jul 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.