Original Budget
$70m
Current Cost
$118m
Cost Overrun
67.5%
47m
Schedule
+36 months
| Sector | Justice & Emergency |
| Responsible Entity | Department of Justice and Community Safety |
| Status | In Progress |
| Original Completion | 30 Jun 2023 |
| Current Completion | 30 Jun 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.