Original Budget
$5m
Current Cost
$23m
Cost Overrun
349.1%
18m
Schedule
+62 months
| Sector | Information Technology |
| Responsible Entity | South East Water Corporation |
| Status | Completed |
| Original Completion | 28 Feb 2020 |
| Current Completion | 30 Apr 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.