[IT] Digital Utility Core Capability
Original TEI
$5.2m
Current TEI
$23.1m
Cost Overrun
+$18.0m
+349.1%
Schedule Overrun
62.0 months
Original: Feb 2020
→ Apr 2025
Cost Status
On Track
Time Status
Off Track
Description
Delivery of end-to-end business processes across meter management, billing and alerts & alarms, enabling customer data linkage for meter monitoring, and improving efficiency in water usage monitoring and leakage detection
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.