Report Card: [IT] Asset Information Management Systems (AIMS) D
Major Overruns
Original Budget
$16m
Current Cost
$28m
Cost Overrun
76.7%
12m
Schedule
+34 months
| Sector | Education & Training |
| Responsible Entity | Department of Education |
| Status | In Progress |
| Original Completion | 30 Sep 2022 |
| Current Completion | 31 Jul 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.