Original Budget
$10m
Current Cost
$10m
Cost Overrun
4.4%
0m
Schedule
+5 months
Sector Transport
Responsible Entity V/Line Corporation
Status In Progress
Original Completion 31 Jul 2026
Current Completion 31 Dec 2026
Scope Changes 0 recorded
Cost RAG On Track
Time RAG At Risk
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.