Original Budget
$89m
Current Cost
$135m
Cost Overrun
51.9%
46m
Schedule
+48 months
| Sector | Justice & Emergency |
| Responsible Entity | Court Services Victoria |
| Status | In Progress |
| Original Completion | 30 Jun 2022 |
| Current Completion | 30 Jun 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | Off Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.