Original Budget
$264m
Current Cost
$517m
Cost Overrun
96.2%
254m
Schedule
+33 months
Sector Transport
Responsible Entity Homes Victoria
Status In Progress
Original Completion 28 Mar 2024
Current Completion 28 Dec 2026
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.