Original Budget
$138m
Current Cost
$181m
Cost Overrun
31.2%
43m
Schedule
+21 months
Sector Water
Responsible Entity Melbourne Water Corporation
Status In Progress
Original Completion 28 Mar 2025
Current Completion 28 Dec 2026
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.