Hobsons Bay Main Yarra crossing duplication (Spotswood)
Original TEI
$138.2m
Current TEI
$181.3m
Cost Overrun
+$43.1m
+31.2%
Schedule Overrun
21.0 months
Original: Mar 2025
→ Dec 2026
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.
Metadata
The estimated completion date has been revised to quarter 2 2026-27 to align with a revised project schedule.