Original Budget
$2,265m
Current Cost
$2,262m
Cost Overrun
-0.1%
-3m
Schedule
+27 months
Sector Transport
Responsible Entity Victorian Rail Track
Status In Progress
Original Completion 28 Sep 2023
Current Completion 28 Dec 2025
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.