High Capacity Metro Trains (metropolitan various)
Original TEI
$2264.8m
Current TEI
$2262.3m
Cost Overrun
$-2.5m
-0.1%
Schedule Overrun
27.0 months
Original: Sep 2023
→ Dec 2025
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.
Metadata
The TEI has decreased by $2.520 million which has been reprioritised to East Pakenham Sub Station (Ryans Road) initiative. The estimated completion date has been revised to quarter 2 2025-26 due to the staging of complex signalling infrastructure works across major projects.