Original TEI
$255.0m
Current TEI
$252.6m
Cost Overrun
$-2.4m
-1.0%
Schedule Overrun
15.0 months
Original: Jun 2025 → Sep 2026
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has decreased by $2.431 million due to budgeted amounts being reclassified as operating instead of capital expenditure, in line with accounting standards. The estimated completion date has been revised to quarter 1 2026-27 due to geotechnical works along the Inland Routes, and complexities with environmental approvals.