Forensic Mental Health Expansion Project Stage 1 and 2 (Fairfield)
Original TEI
$462.5m
Current TEI
$462.5m
Cost Overrun
$0.0m
0.0%
Schedule Overrun
12.0 months
Original: Jun 2025
→ Jun 2026
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.
Metadata
The main works will be completed by quarter 1 2025-26, with the estimated completion date revised to quarter 4 2025-26 due to decanting, refurbishment works and in line with a revised project schedule for the multi-deck car park.