Report Card: Fishermans Bend Innovation Precinct at the former General M… B
Minor Issues
Original Budget
$179m
Current Cost
$198m
Cost Overrun
10.2%
18m
Schedule
+6 months
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | In Progress |
| Original Completion | 28 Dec 2025 |
| Current Completion | 28 Jun 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.