Original TEI
$179.4m
Current TEI
$197.7m
Cost Overrun
+$18.3m
+10.2%
Schedule Overrun
6.0 months
Original: Dec 2025 → Jun 2026
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has increased by $18.300 million due to additional remediation work. The estimated completion date has been revised to quarter 4 2025-26 in line with a revised project schedule.