Report Card: Delivering the Road Safety Action Plan (statewide) B
Minor Issues
Original Budget
$230m
Current Cost
$271m
Cost Overrun
17.7%
41m
Schedule
On Time
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | In Progress |
| Original Completion | 28 Jun 2028 |
| Current Completion | 28 Jun 2028 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.