Original Budget
$741m
Current Cost
$884m
Cost Overrun
19.3%
143m
Schedule
+12 months
Sector Transport
Responsible Entity Major Transport Infrastructure Authority
Status In Progress
Original Completion 30 Jun 2024
Current Completion 30 Jun 2025
Scope Changes 0 recorded
Cost RAG At Risk
Time RAG At Risk
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.