Cranbourne Line Duplication
Original TEI
$741.0m
Current TEI
$884.0m
Cost Overrun
+$143.0m
+19.3%
Schedule Overrun
12.0 months
Original: Jun 2024
→ Jun 2025
Cost Status
At Risk
Time Status
At Risk
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.
Contractors & Partners
| Contractor | Type | Role | Contract Value |
|---|---|---|---|
| Laing O'Rourke | Builder / Constructor | South Eastern Program Alliance — Merinda Park Station | $180.0m |
| McConnell Dowell | Builder / Constructor | Western Program Alliance — Track Duplication | $501.0m |
Metadata
Duplication of single-track section on Cranbourne line.