Original TEI
$741.0m
Current TEI
$884.0m
Cost Overrun
+$143.0m
+19.3%
Schedule Overrun
12.0 months
Original: Jun 2024 → Jun 2025
Cost Status
At Risk
Time Status
At Risk
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Contractors & Partners
Contractor Type Role Contract Value
Laing O'Rourke Builder / Constructor South Eastern Program Alliance — Merinda Park Station $180.0m
McConnell Dowell Builder / Constructor Western Program Alliance — Track Duplication $501.0m
Metadata

Duplication of single-track section on Cranbourne line.