Projects Involved
3
Total Project Exposure
$17484m
combined current TEI
Projects Over Budget
3
of 3 total
Combined Overrun
+$6693m
Political Donations
$0
0 recorded donations
Sector Exposure
Transport
$17484m
3 projects
Project Portfolio
Project Role Sector Original TEI Current TEI Overrun Cost Time
Level Crossing Removal Program Western Program Alliance Transport $8300m $14500m +$6200m
Regional Rail Revival Geelong Line — South Geelong to … Transport $1750m $2100m +$350m
Cranbourne Line Duplication Western Program Alliance — Track Duplication Transport $741m $884m +$143m