Projects Involved
3
Total Project Exposure
$50384m
combined current TEI
Projects Over Budget
3
of 3 total
Combined Overrun
+$29543m
Political Donations
$0
0 recorded donations
Sector Exposure
Transport
$50384m
3 projects
Project Portfolio
Project Role Sector Original TEI Current TEI Overrun Cost Time
Suburban Rail Loop East — Development & Early … Initial and Early Works Transport $11800m $35000m +$23200m
Level Crossing Removal Program South Eastern Program Alliance Transport $8300m $14500m +$6200m
Cranbourne Line Duplication South Eastern Program Alliance — Merinda … Transport $741m $884m +$143m