Projects Involved
2
Total Project Exposure
$16600m
combined current TEI
Projects Over Budget
2
of 2 total
Combined Overrun
+$6550m
Political Donations
$0
0 recorded donations
Sector Exposure
Transport
$16600m
2 projects
Project Portfolio
| Project | Role | Sector | Original TEI | Current TEI | Overrun | Cost | Time |
|---|---|---|---|---|---|---|---|
| Level Crossing Removal Program | Southern Program Alliance | Transport | $8300m | $14500m | +$6200m | ||
| Regional Rail Revival | Shepparton Line — Stage 2 | Transport | $1750m | $2100m | +$350m |