Projects Involved
2
Total Project Exposure
$16600m
combined current TEI
Projects Over Budget
2
of 2 total
Combined Overrun
+$6550m
Political Donations
$0
0 recorded donations
Sector Exposure
Transport
$16600m
2 projects
Project Portfolio
Project Role Sector Original TEI Current TEI Overrun Cost Time
Level Crossing Removal Program Western Program Alliance — Design Transport $8300m $14500m +$6200m
Regional Rail Revival Geelong Line — Design Transport $1750m $2100m +$350m