Original TEI
$590.5m
Current TEI
$610.3m
Cost Overrun
+$19.7m
+3.3%
Schedule Overrun
0.0 months
Original: Dec 2025 → Dec 2025
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has increased by $19.737 million due to additional Commonwealth Government funding for its remaining 50 per cent share of some joint projects. The TEI includes $141.740 million of Commonwealth Government funding.