Original Budget
$1,118m
Current Cost
$1,120m
Cost Overrun
0.2%
2m
Schedule
+24 months
Sector Health & Human Services
Responsible Entity Department of Health
Status In Progress
Original Completion 28 Mar 2026
Current Completion 28 Mar 2028
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.