Report Card: Building a better hospital for Melbourne's inner west (Foot… A
On Track
Original Budget
$1,999m
Current Cost
$1,999m
Cost Overrun
0%
Schedule
+3 months
| Sector | Health & Human Services |
| Responsible Entity | Department of Health |
| Status | In Progress |
| Original Completion | 28 Sep 2025 |
| Current Completion | 28 Dec 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.