Original Budget
$3,067m
Current Cost
$2,247m
Cost Overrun
-26.7%
-820m
Schedule
+9 months
| Sector | Housing |
| Responsible Entity | Homes Victoria |
| Status | In Progress |
| Original Completion | 28 Sep 2027 |
| Current Completion | 28 Jun 2028 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.