Report Card: Best Start, Best Life: Infrastructure 2023-24 (statewide) A
On Track
Original Budget
$2,221m
Current Cost
$2,220m
Cost Overrun
0.0%
-1m
Schedule
On Time
| Sector | Education & Training |
| Responsible Entity | Department of Education |
| Status | In Progress |
| Original Completion | 28 Jun 2031 |
| Current Completion | 28 Jun 2031 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.