Original Budget
$365m
Current Cost
$359m
Cost Overrun
-1.7%
-6m
Schedule
+21 months
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | In Progress |
| Original Completion | 28 Dec 2023 |
| Current Completion | 28 Sep 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.