Projects Analysed
576
Over Budget
202
35.1% of all projects
Average Overrun
20.1%
across all projects
Key Findings
Factor 1: Sector
Average Overrun by Sector Sectors with 3+ projects
Sector Projects Avg Overrun Over Budget Original TEI Current TEI Total Overrun
Water 91 56.1% 39 (43%) $22.6b $35.4b $12.8b
Information Technology 124 18.5% 49 (40%) $1.1b $1.3b $0.2b
Justice & Emergency 46 16.7% 19 (41%) $4.6b $5.0b $0.3b
Transport 136 15.5% 40 (29%) $191.1b $244.4b $53.3b
Education & Training 39 12.8% 11 (28%) $9.7b $9.8b $0.1b
Health & Human Services 119 6.3% 37 (31%) $26.9b $27.2b $0.3b
Housing 9 4.5% 4 (44%) $10.6b $9.9b $-0.7b
Culture, Sport & Community 3 2.1% 1 (33%) $3.5b $3.6b $0.1b
Other 9 -0.0% 2 (22%) $3.3b $3.3b $0.0b
Factor 2: Project Size
Average Overrun by Original TEI Band Does bigger mean more risk?
Size Band Projects Avg Overrun Over Budget
< $100m 272 19.4% 105 (39%)
$100–500m 218 25.0% 65 (30%)
$500m–1b 40 5.4% 16 (40%)
$1–5b 31 4.3% 9 (29%)
> $5b 15 32.6% 7 (47%)
Factor 3: Size vs Overrun Correlation
Original TEI vs Cost Overrun % Each dot is a project. Colour = sector.
Top 15 Worst Cost Blowouts
# Project Sector Original TEI Current TEI Overrun % Overrun $m
1 Land development projects (statewide) Water $219m $2,872m +1212.4% +$2,653m
2 Eastern treatment plant projects (Bangholme) Water $286m $2,534m +787.2% +$2,248m
3 [IT] Victorian Transport Digital Engineering Transform… Transport $5m $45m +777.2% +$40m
4 Western treatment plant projects (Werribee) Water $215m $1,687m +683.6% +$1,472m
5 Drainage and flood projects (statewide) Water $116m $692m +496.0% +$576m
6 [IT] Digital Utility Core Capability Information Technology $5m $23m +349.1% +$18m
7 Sewer collection – main sewers (regional various) Water $248m $1,031m +315.9% +$783m
8 [IT] Regional Community Care Coordination Platform Health & Human Services $1m $5m +240.6% +$3m
9 Suburban Rail Loop East — Development & Early Works Transport $11,800m $35,000m +196.6% +$23,200m
10 [IT] Network Architecture Improvements SDWAN Information Technology $1m $3m +191.6% +$2m
11 [IT] Better Technology Tools Enabling Responsibility (… Justice & Emergency $19m $54m +183.4% +$35m
12 [IT] Integrated supervised contact and access solution Information Technology $1m $3m +168.9% +$2m
13 Homes Victoria Ground Lease Model Project 2 (metropoli… Transport $260m $687m +164.3% +$427m
14 [IT] C1062 - Works and Asset Management Information Technology $1m $2m +163.4% +$1m
15 [IT] Trusted and Secure Program Transport $7m $17m +155.3% +$11m
Methodology: Overrun % = (Current TEI - Original TEI) / Original TEI × 100. Original TEI is from the earliest available Budget Paper 4 snapshot. Current TEI is from BP4 2025-26. Only projects with TEI > $0 are included. Data source: Victorian Budget Paper 4 (State Capital Program) and IT Dashboard.